End in sight for long-running stop-go system in busy Kilkenny town where quay wall is falling into river


Kilkenny County Council expect work to start in Thomastown in May
Light at the end of the tunnel is emerging for drivers dealing with the long-running stop-go system along the quay in Thomastown.
Works to repair the issue of subsidence along the river wall, which is causing the lane closure on the road into the town, is set to start in the coming weeks.
At the April meeting of Callan Thomastown municipal district councillors, it was announced that a plan has been agreed and work should start next month.
READ NEXT: Fresh call to introduce pay-parking in the centre of Thomastown - to help local businesses
Area Engineer, Declan Murphy, said the proposed works include the installation of 55 metres of rock bag protection which will stabilise the base of the quay wall. An impermeable membrane will be installed between the rock bags and the wall.
On the road side of the wall, the road substrate will be ‘grouted’ following which the road will be resurfaced.
To facilitate this work the council has asked ESB to remove the overhead cables along the route. This is essential to allow the installation of the rock bags, Mr Murphy explained. He said it has been explained to the ESB that this is for emergency works.
However, the ESB response is ‘the one unknown’ is the plan, Mr Murphy said. Without lifting the lines the contractors will not be able to lift the rock bags into the river.
Contractors have advised that, all going well, they will be on-site approximately mid-May. It is hoped the work will be finished by the end of June.