Progress continues on North Quays project - Kilkenny Live

Progress continues on North Quays project - Kilkenny Live

Artist's impression of North Quays project

Works are continuing apace at the North Quays site on the Kilkenny side of the River Suir.

Traffic management has been in place on the Dock Road since June 26 and will remain in place until 2024.

The construction of a satellite compound at the South Plaza is now also substantially completed.

Site clearance is circa 25% completed and site fencing and hoarding erection is continuing.

The construction of a temporary piling platform at the Transport Hub has also commenced.

A revised programme is now in place for the works at Ferrybank Pump Station.

The handover date is now January 4, 2024 instead of November 24, 2023.

This delay was caused by the necessity to align the electrical work fit out with the completion date of the building.

Over the next three months, it is expected that cofferdams will be laid in the Suir for the planned new bridge to Waterford City and works will progress further at the South Plaza and Transport Hub.

To continue reading this article,
please subscribe and support local journalism!


Subscribing will allow you access to all of our premium content and archived articles.

Subscribe

To continue reading this article for FREE,
please kindly register and/or log in.


Registration is absolutely 100% FREE and will help us personalise your experience on our sites. You can also sign up to our carefully curated newsletter(s) to keep up to date with your latest local news!

Register / Login

Buy the e-paper of the Donegal Democrat, Donegal People's Press, Donegal Post and Inish Times here for instant access to Donegal's premier news titles.

Keep up with the latest news from Donegal with our daily newsletter featuring the most important stories of the day delivered to your inbox every evening at 5pm.