Kilkenny's largest water plant had disinfection units overdue for service

Aerial view of Troyswood Water Treatment Plant in Kilkennyplaceholder image
Aerial view of Troyswood Water Treatment Plant in Kilkenny | File Photo

EPA audit of Troyswood Water Treatment Plant (serving c. 29,269 people) found servicing and procedural gaps but said the Kilkenny supply was ‘operating satisfactorily’

An Environmental Protection Agency (EPA) audit produced earlier this year found that two ultraviolet disinfection units at Kilkenny’s Troyswood Water Treatment Plant were outside their servicing/calibration intervals during an inspection, although the plant was “operating satisfactorily”.

Uisce Éireann also confirmed to the EPA that there was no documented, site-specific alarm-response procedure and that site-specific procedure for checking alarms and automatic shutdown controls after maintenance or other work was also absent.

The announced inspection took place on May 25, 2026. The report, issued on June 17, records 29,269 people served by the supply, using 2025 figures.

The EPA recommended documenting both procedures and training relevant staff, including relief and temporary personnel. It also recommended servicing/calibrating the UV units and attaching stickers showing appropriate service intervals.

The utility was asked to report on action taken and planned. The audit does not report contaminated water or a disinfection failure, or specify how long the units were overdue.

This audit was carried out to assess the performance of Uisce Éireann in providing clean and wholesome water to the public water supply.

BACKGROUND

In October 2024, Uisce Éireann announced the completion of a €33 million investment in Kilkenny’s water supply. The project expanded Troyswood, added a new River Nore intake and pumping facilities, and included a 2.9-kilometre water main connecting Troyswood to the Radestown site.

The company said the work enabled Radestown’s treatment plant to be decommissioned and the supply previously served by it to be removed from the EPA’s Remedial Action List. Troyswood became the main treatment facility for Kilkenny City.

An earlier EPA inspection, in September 2024, recorded satisfactory operation of the plant’s disinfection systems. It also recommended appropriate staff training before the planned transfer of plant operations from contractor Glanua to Uisce Éireann.

That report described a contractor operation-and-maintenance period due to run until June 2025, with training planned before handover. It does not establish what training subsequently took place.

The 2026 audit does not attribute its findings to the handover. Nor does the published report establish whether its three recommendations have since been completed.

Uisce Éireann and the EPA have been approached for comment.