Kilkenny commuters get fresh boost as North Quays work advances


New progress has been confirmed on the North Quays sustainable transport bridge, transport hub and South Kilkenny greenway connections as work continues towards public opening...
Kilkenny commuters and cyclists are a step closer to benefiting from the long-awaited North Quays development, with new progress confirmed on the sustainable transport bridge linking Ferrybank to Waterford City.
A recent project update shows the bridge has reached another significant milestone, with the installation of edge railings, glass panels and pedestrian barriers now well advanced.
Remaining works, including surfacing, lighting, street furniture and commissioning of the bridge's automated opening span, will continue over the summer. The bridge remains on course to open to the public in 2027.
The crossing is expected to transform access between Ferrybank and Waterford City for pedestrians and cyclists, while also providing a direct connection to the new transport hub.
The update also confirms that work on the transport hub is progressing, with internal fit-out works continuing, access lifts installed and testing of the station's operational systems due to begin in the coming months. A new southern entrance to the station will also be constructed.
Iarnród Éireann is continuing work on signalling, electrical and telecommunications systems, with the station expected to open towards the end of 2027.
For residents in South Kilkenny, the project also brings further improvements to active travel links.
Infrastructure works on Abbey Road are complete, while the new greenway ramp at Abbey Road has opened, allowing public access to a six-kilometre section of the South-East Greenway towards Curraghmore.
The report notes that railway flood defence works remain a critical element of the overall project. Several phases have been completed, with further works to begin later this year. The entire flood defence scheme must be completed before the transport hub can open.