Kilkenny councillors query tripling of overall greenway delivery cost

File photo of construction work on the South-East Greenwayplaceholder image
File photo of construction work on the South-East Greenway | www.southeastgreenway.net

Director of Services at Kilkenny County Council, Tony Lauhoff, provided an update on the South-East Greenway project at the most recent meeting of Piltown Municipal District

The South-East Greenway is now expected to cost around €45 million to deliver, more than three times the original 2019 estimate.

That figure was revealed at the most recent monthly meeting of Piltown Municipal District, held at Ferrybank Library.

Back in 2019, the overall project cost was reported to be €13.3 million, including an approved €8 million grant from the Department of Transport Tourism and Sport.

Cllr Pat Dunphy stated that he ‘couldn’t believe’ the newly revised figure and called for clarity on the matter for the next district meeting.

Director of Services at Kilkenny County Council, Tony Lauhoff, further updated members that “of the 24 kilometres of the greenway, some 14 kilometres are now substantially complete, with 12 kilometres now open to the public.”

The project design team are continuing to progress the detailed design of the section of greenway between Curraghmore and Ballyverneen in south Kilkenny, which is approximately 9km in length.

The landowner liaison team are continuing to engage with affected landowners along this section to agree final design layouts and accommodation works.

Separately, plans are advancing on the proposed Pink Rock Cycle Loop and Amenity Trail.

This loop/trail would run between the South-East Greenway car park at Ballyverneen and Annagh’s Bridge along the Pink Rock Road.

According to the local authority, the proposed cycle loop “will provide a scenic recreational opportunity for locals and visitors and allow users to take an alternative route to the greenway following the scenic banks of the River Barrow crossing under the Rose Fitzgerald Kennedy Bridge.”

The greenway project design team are also continuing to work on proposed links between the greenway and the villages of Glenmore and Slieverue.

For Glenmore, discussions with the affected landowners will continue with regard to the acquisition of lands required to deliver the project.

The same is true for Slieverue, where it is intended to make an application for the project under the Outdoor Recreation Infrastructure Scheme this quarter.

Plans to link the greenway to Woodstock (Inistioge) are also advancing and a preferred route corridor option will be proposed soon.

When the announcement is made, a third round of public consultation will be held on the proposed preferred route corridor option.

The South-East Greenway is due to provide an attractive amenity for visitors to the region as well as providing an environmentally friendly alternative for commuters into Waterford and New Ross.

The Greenway follows the line of the disused New Ross to Waterford railway, and passes predominantly through rural Kilkenny.

It will ultimately form part of a longer greenway from St Mullins in Carlow to the Waterford Greenway and Dungarvan.

Powered by