The North Quays main contract has made significant progress in the last two months, councillors in South Kilkenny were informed at the latest meeting of Piltown Municipal District.
Substructure works for the sustainable transport bridge over the River Suir is continuing, with all four cofferdams operational and work is progressing internally with the formation of the bridge piers.
Read next: Alleged incidents of stone throwing and anti-social behaviour in area of Kilkenny
The fabrication of the steel deck superstructure for the bridge is now close to completion in Belgium, and the sections are currently being painted.
The transport hub building works are continuing with the support walls and columns complete.
The construction of the southern platform blockwork at platform level has commenced and the construction of the northern platform boundary wall is ongoing.
Road and access infrastructure is also progressing well, with works continuing on the various bridge structures.
Traffic management measures continue to be in place, with various works continuing.
Uisce Eireann is now operating the pump station in Ferrybank.
Also, flood relief scheme site investigations and detailed design are progressing well.
Subscribe or register today to discover more from DonegalLive.ie
Buy the e-paper of the Donegal Democrat, Donegal People's Press, Donegal Post and Inish Times here for instant access to Donegal's premier news titles.
Keep up with the latest news from Donegal with our daily newsletter featuring the most important stories of the day delivered to your inbox every evening at 5pm.